So...progress! Was real nice today with low of 50; high 66*F!
1 week on the tomatoes...
with all the record warmth for the last week, they have doubled in size...great start! Ready to trim the lower leaves and mound some more dirt around the vine. Helps to make a HUGE root ball and more roots=more fruits!
Hurricane clips... on everything @4 spacing...
I sistered a 2x4 to the 2x8 floor joist for a full 1.5" of surface contact with the ends of the plywood sheet. Also blocked perpendicular to the joists with 2x4's turned sideways along where the seams of where the plywood meet. That, screws, and liberal amount of sub-floor glue should do it.
Got the first tie down anchor banding installed...
Plumb. level and square...
3 more to go and I can install the plywood decking. Hope to have that done by midday tomorrow, then start on the wall framing. Hope to have the wall framing, roof trusses, perlings, and roof tin on before Friday. That is the next rain coming thru with another cool front.
Shout out to chopsaw for answering my questions. Been a big help!