The footings are the bare minimum i can do. Since then i have decided to do a footing and grade beam so its one monolithic pour, 12" thick. Im loosing good weather and the concrete company I deal with is shutting down for the season at the end of the month, i lost my window so i have lots of time now to make a massive pad with lots of steel. I looks like im crawling around on the floor for a bit longer. As far as the 4 vs 2 post, i decided of the two because it takes up less space and i don't need storage really. This hoist is dedicated for vehicle service so having the wheels free and off the ground was a big reason for that. I could have gone with a 4 post plus the inner jacks but each jack was 2/3 the cost of the hoist. We would have been pushing $15000 or more dollars.
Corey