Hi. I am building a vertical smoker with a firebox on the side, all in the same cabinet.
Day 1:
Brought home some metal and started cutting and welding.
Basic frame, 50" x 43" x 30" Fire box will be on the right in that smaller section.
Here is what it looks like right now:
Pile 'o steel:
Cutting mineral wool with a steak knife for the tubing:
I found I needed to use a broom handle and a large washer to push the insulation all the way to the end of the tubing.
Repeat until full.
Day 1:
Brought home some metal and started cutting and welding.
Basic frame, 50" x 43" x 30" Fire box will be on the right in that smaller section.
Here is what it looks like right now:
Pile 'o steel:
Cutting mineral wool with a steak knife for the tubing:
I found I needed to use a broom handle and a large washer to push the insulation all the way to the end of the tubing.
Repeat until full.
Last edited: